Progress Updates and Look Aheads

Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.

Also available on this  page are past updates and special notices.

For additional information, please use the following links:

Cultural Resource Updates

Environmental Monitoring Data Updates

Progress Update, Week of April 11th, 2022

During the week of April 11 the Gowanus Remediation Team (GRT) conducted In-Situ Stabilization (ISS) near the Carroll Street Bridge early in the week, before temporarily suspending ISS operations in order to commence Phase 2 dredging.

Progress Update, Week of March 28th, 2022

During the week of March 28 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS). The ISS work barges were relocated to conduct ISS near the Carroll Street Bridge.

Progress Update, Week of March 21st, 2022

During the week of March 21 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge. At Degraw Street the tieback installations