Skip to content

Progress Update, Week of November 22, 2021

During the week of November 22, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal. Sheet piles were prepared for installation.

Pipe pile cutting at the Carroll Street Bridge was completed. Pipe piles that were installed within the navigational channel were cut to an appropriate height.

Analysis of the In-Situ Stabilization (ISS) demonstration test results remains ongoing. Mobilization for full scale ISS will begin over the coming weeks.

Photos of construction activities are provided below.

Cutting pipe piles at the southwest corner of the Carroll Street bridge.
Starter sheet piles installed at the headwall.