Progress Update, Week of November 15, 2021

During the week of November 15, the Gowanus Remediation Team began installing sheet pile bulkheads near the head of the canal.

Pipe pile cutting continued at the Carroll Street Bridge.  Pipe piles that were installed within the navigational channel are being cut to an appropriate height.

Analysis of the In-Situ Stabilization (ISS) demonstration test results is ongoing. Mobilization for full scale ISS will begin over the coming weeks.

Photos of construction activities are provided below.

Photograph #2 – Mini hopper with Giken/auger landed at the 50’ x 160’ platform.

Continued pipe pile cutting at the Carroll Street bridge.

Moving a sheet pile on location near the head of the canal.

Installing a sheet pile.